Work in progress:
Augercast pile installation continues in the SE corner of the site. Currently 315 piles have been installed and 30 remain.
Pile cap and grade beam forming and installation has begun.
Basement retaining walls forming to begin 2/25/16.
Elevator #1 (…
Work in Progress:
CMU wall in the receiving and student machine shop is complete.
Working on electrical raceways on the second floor.
Completed demolition on the second floor.
Looking ahead:
Carpenters to start layout & framing on Monday in 101…
Work in progress:
Augercast pile installation continues in the SW corner of the site and elevator #2 (South Elevator).
Work in progress:
Currently removing the louver on the 3rd floor west mechanical room.
Continuing the chilled water piping in the 3rd floor east mechanical room.
Started the demolition of AHU#3 in the 3rd floor west mechanical room.
Electrician has started ductbank for MCC…
Image
Mietek Jaroniec, Ph.D., is a professor in the Department of Chemistry and Biochemistry at Á½ÐÔÉ«ÎçÒ¹ University and one of the top researchers in the field of advanced materials. His recent research is focused on nanomaterials (specifically nanoporous carbon spheres),…
Work in progress:
Completed AHU #3 duct tie-in to AHU #2.
Air handler unit #3 has been permanently shutdown.
Start layout for tele/data ductbanks.
Starting motor control center (MCC) and swithgear duct bank.
Started mass excavation - currently 95% complete.
Work in progress:
Site shoring around the building is complete - contractor is demobilizing.
130 Piles are complete on the north end of the site (approximately to column line 7).
Temporary ramp into excavation is complete.
Sanitary tie-in on the north side has been…
Image
On February 2, Á½ÐÔÉ«ÎçÒ¹ students in the College of Arts and Sciences Learning Community were given a unique opportunity to hear a former United States Ambassador speak on foreign policy issues and U.S.-Russian relations. Steven Pifer, who formerly served as the U.S. Ambassador…
Work in Progress:
Continuing the installation of the temporary duct and assembly of new AHU1 in the East side mechanical room.
Stripped topsoil from addition footprint.
Phoenix air valve replacement in the Annex research labs continues per schedule.
Continue …