Work in Progress:
- Forming at stair #3 for 3rd lift continues; 2nd lift pour has been completed.
 - Concrete piers along column line 'B' were completed.
 - Steel erection in sequence 1 - 4 continues.
 - Steel detailing in sequence 2 continues.
 - Basement retaining wall between column line 17/A.1 to 17/C in progress.
 - Steam, steam condensate and chilled water piping work in tunnel is in progress.
 - Removal of temporary overhead protection at Williams Hall dock area.
 - Chilled water line installation in Williams Hall mechanical room continues.
 
Looking forward:
- Start installation on steel sequence #5 & #6.
 - Continue steel sequence #3 detailing.
 - Continue work at elevator #2 for 3rd concrete pour.
 - Complete forming for 3rd concrete pour next week.
 - Continue utility work in tunnels.